Lot-sizing, time-phased netting, and multi-level MRP (BOM explosion) for logistics-ts.
Readme
@logistics-ts/planning
Production and inventory planning for
logistics-ts: the lot-sizing
family that turns a per-period demand vector into a costed order plan, and the
time-phased netting grid (MRP record) that decides what actually needs
ordering in the first place. Every result returns Explained<T> — the plan,
plus the method, inputs, reasoning, and citations behind it.
Scope is deliberate: MRP is infinite-capacity by definition, so capacity planning (CRP), scheduling and routings are not included.
Install
npm i @logistics-ts/planningWhat's in it
lotSize— one entry point that dispatches to any rule below by name, for when the rule is chosen at runtime (config, UI, or an agent).wagnerWhitin— the dynamic-programming optimum.lotForLot,fixedOrderQuantity,periodOrderQuantity,silverMeal,leastUnitCost— the classic MRP heuristics.accumulateLotCost/simulateLotCost— the low-level cost primitives every rule shares, so all plans are costed the same way.
Choosing a rule
| Rule | lotSize name | Optimal? | Trade-off |
|---|---|---|---|
| wagnerWhitin | 'wagner-whitin' | Yes — provably minimum cost | O(T²) dynamic program. Cheap for any realistic horizon; prefer this unless you specifically need a heuristic's behaviour. |
| lotForLot | 'lot-for-lot' | No | Orders each period's demand in that period. Zero holding, maximal ordering — the MRP baseline. |
| fixedOrderQuantity | 'foq' | No | Fixed lot Q repeated as needed. The only rule that can leave surplus inventory at the horizon end. Requires orderQuantity. |
| periodOrderQuantity | 'poq' | No | Orders at a fixed interval derived from the EOQ anchor. |
| silverMeal | 'silver-meal' | No | Greedy: extends a run while average cost per period falls. Can be arbitrarily worse than the optimum on adversarial demand. |
| leastUnitCost | 'least-unit-cost' | No | Greedy: extends a run while cost per unit falls. Same local-stopping weakness. |
The heuristics are greedy local rules — each stops at the first upturn in its
criterion and never revisits an earlier run boundary, so none is optimal. They
are included because they are the textbook MRP defaults and are what many
existing systems implement; when cost is what matters, use wagnerWhitin.
All rules share one end-of-period holding convention (holding is charged on
inventory carried out of each period), so their costs are directly comparable —
and wagnerWhitin is golden-tested against Python
stockpyl's wagner_whitin, reproducing
Snyder & Shen, Fundamentals of Supply Chain Theory 2e, Example 3.9.
Quick start
import { lotSize, wagnerWhitin } from '@logistics-ts/planning'
const demand = [90, 120, 80, 70] // units per period
const costs = { setupCost: 500, holdingCostPerUnitPerPeriod: 2 }
const plan = wagnerWhitin(demand, costs)
plan.value.orders // [{ period: 0, quantity: 210 }, { period: 2, quantity: 150 }]
plan.value.totalCost // 1380 (setup 1000 + holding 380)
plan.reasoning // why each order exists
plan.citations // ['Wagner, H.M. & Whitin, T.M. (1958), Management Science 5(1), 89-96', ...]
// Same thing when the rule is selected at runtime:
lotSize(demand, { rule: 'wagner-whitin', ...costs })
// 'foq' is the one rule needing an extra option — and the types enforce it:
lotSize(demand, { rule: 'foq', ...costs, orderQuantity: 150 })Costs use consistent units: demand in units/period, setupCost in
currency/order, and holdingCostPerUnitPerPeriod in currency/unit/period.
Time-phased netting grid (MRP record)
Lot sizing answers how much to order at once. mrpGrid answers the prior
question — what actually needs ordering, once existing stock, open orders, and
a safety-stock floor are accounted for. It is the canonical MRP record (Orlicky;
APICS/ASCM CPIM), one row per period:
| column | meaning |
| --- | --- |
| grossRequirements | demand in the period |
| scheduledReceipts | open orders already due |
| projectedAvailableBalance | stock at end of period; never below safetyStock |
| netRequirements | max(0, GR + safetyStock − PAB_prev − SR) |
| plannedOrderReceipt | lot-sized order arriving in the period |
| plannedOrderRelease | that receipt offset left by leadTimePeriods |
import { mrpGrid } from '@logistics-ts/planning'
const plan = mrpGrid({
grossRequirements: [10, 0, 40, 30, 0, 50],
scheduledReceipts: [0, 0, 15, 0, 0, 0],
onHand: 20,
leadTimePeriods: 2,
})
plan.value.rows.map((r) => r.netRequirements) // [0, 0, 15, 30, 0, 50]
plan.value.rows.map((r) => r.plannedOrderRelease) // [15, 30, 0, 50, 0, 0]
plan.value.plannedOrders
// [{ releasePeriod: 0, receiptPeriod: 2, quantity: 15, pastDue: false }, ...]
plan.reasoning // narrates each order: what caused it, what sized it, when to releaseSafety stock is netted against as if it were extra demand, so
projectedAvailableBalance never drops below the floor — this pulls orders
earlier and larger.
Lot rules are pluggable and default to lot-for-lot. The grid hands the
whole net-requirements vector to lotSize rather than sizing period by
period, because Silver-Meal and Wagner-Whitin are horizon algorithms:
mrpGrid({
grossRequirements: [40, 60, 0, 90, 70],
onHand: 55,
safetyStock: 15,
lotRule: { rule: 'wagner-whitin', setupCost: 300, holdingCostPerUnitPerPeriod: 2 },
})Lead time is in periods (buckets), never days. leadTimePeriods: 2 on a
weekly grid means two weeks — convert a day-denominated supplier lead time
before calling.
Past-due orders are surfaced, not hidden. If a release would land before
period 0, the receipt is kept (the demand is real) and reported both in
warnings and in plannedOrders with pastDue: true — never silently dropped
or clamped into period 0. A planner needs to know the plan is infeasible as
scheduled.
Multi-level MRP (BOM explosion)
mrpGrid plans one item. planRequirements plans a whole product structure:
master schedule in, netted and lot-sized planned orders for every component out.
import { planRequirements } from '@logistics-ts/planning'
const plan = planRequirements({
bom: [
{ parentId: 'BIKE', childId: 'WHEEL', quantityPer: 2 },
{ parentId: 'WHEEL', childId: 'SPOKE', quantityPer: 32 },
],
masterSchedule: [{ itemId: 'BIKE', requirements: [0, 0, 0, 0, 100] }],
items: {
BIKE: { leadTimePeriods: 1 },
WHEEL: { leadTimePeriods: 2, onHand: 40 },
SPOKE: { leadTimePeriods: 1 },
},
})
plan.value.order // ['BIKE', 'WHEEL', 'SPOKE']
plan.value.items.WHEEL.grossRequirements // driven by BIKE's RELEASES
plan.value.items.SPOKE.rows // full time-phased recordDated records in, periods out
Every planning function is indexed by period (bucket), and leadTimePeriods
counts those same buckets — at weekly buckets a 10-day lead time is 2. Turn
dated master-schedule rows into that shape with toMasterSchedule:
import { toMasterSchedule } from '@logistics-ts/planning'
const { masterSchedule, periods } = toMasterSchedule(
[
{ itemId: 'BIKE', date: '2026-03-02', quantity: 100 },
{ itemId: 'BIKE', date: '2026-03-16', quantity: 150 },
],
'week',
)
periods // ['2026-03-02', '2026-03-09', '2026-03-16']
masterSchedule[0] // { itemId: 'BIKE', requirements: [100, 0, 150] }It aligns every item to one shared calendar, which is why it exists rather
than a bare bucketize call: bucketize defaults each item to that item's own
earliest and latest demand, which is right for forecasting and silently wrong
here, where period 0 must mean the same period for every item. Pass start to
pin period 0 to a real date such as today.
Pass periods on to planRequirements and it is echoed back on the result, so a
planned order can be reported against a date instead of an index.
Components are driven by their parents' planned order releases, not their gross requirements. A parent that must be started in period 3 needs its components in period 3 — not in period 5 when the finished parent arrives — and netting the parent first means its own stock and lead time are already taken into account. This is the difference between MRP and a naive explosion.
Items are processed in low-level-code order, where a low-level code is the longest path from an end item. A component used at two different depths is therefore planned only after every one of its parents, so it is never understated. A cyclic BOM is rejected with the offending edge named.
If you only want dependent gross requirements without any netting, explode(bom,
demand) is the standalone gross explosion:
import { explode } from '@logistics-ts/planning'
explode(
[{ parentId: 'A', childId: 'B', quantityPer: 2 }],
[{ itemId: 'A', requirements: [0, 100] }],
).value.grossRequirements.B // [0, 200]Past-due releases are escalated. If a parent must be released before period 0
and has components beneath it, those components' requirements are
understated — the demand cannot be scheduled at all — and the result says so
in warnings. A component's own plan has no way to report that.
In the umbrella package
@logistics-ts/planning is re-exported as the planning namespace from
logistics-ts:
import { planning } from 'logistics-ts'
planning.wagnerWhitin([90, 120, 80, 70], { setupCost: 500, holdingCostPerUnitPerPeriod: 2 })
planning.mrpGrid({ grossRequirements: [10, 0, 40], onHand: 20, leadTimePeriods: 1 })@logistics-ts/planning sits above @logistics-ts/inventory in the layering, so
it may import inward from any lower layer — but it declares only what it actually
uses: @logistics-ts/core (the Explained result type and numeric primitives)
and @logistics-ts/inventory (it reuses that package's eoq as the anchor for
the period-order-quantity interval).